johannesburg environmental copper mine pendulum feeder price

johannesburg environmental copper mine pendulum feeder price

The Kamoa-Kakula Copper Project — a joint venture between Ivanhoe Mines (39.6%), Zijin Mining Group (39.6%), Crystal River Global Limited (0.8%) and the Government of the Democratic Republic of Congo (20%) — has been independently ranked as the world's largest, undeveloped, high-grade copper discovery by international mining consultant Wood Mackenzie. It is a very large, near-surface, flat-lying, stratiform copper deposit with adjacent prospective exploration areas within the Central African Copperbelt, approximately 25 kilometres west of the town of Kolwezi and about 270 kilometres west of the provincial capital of Lubumbashi

[email protected]

Hot Crushing Plant Brief Introduction

We are a professional mining machinery manufacturer, the main equipment including: jaw crusher, cone crusher and other sandstone equipment;Ball mill, flotation machine, concentrator and other beneficiation equipment; Powder Grinding Plant, rotary dryer, briquette machine, mining, metallurgy and other related equipment.If you are interested in our products or want to visit the nearby production site, you can click the button to consult us.

Initial production at the Kakula Mine processing plant is scheduled in July 2021. Kakula is projected to be the world’s highest-grade major copper mine, with an initial mining rate of 3.8 million tonnes per annum (Mtpa) at an estimated average feed grade of more than 6.0% copper over the first five years of operation. Kakula is the first of multiple, planned, high-grade mining areas on the 400-square-kilometre Kamoa-Kakula mining licence. 

The Kakula Mine will have one of the most favourable environmental footprints of any tier-one copper mine worldwide. The mine will be powered by clean, renewable hydroelectricity and be among the world's lowest greenhouse gas emitters per unit of copper produced. Kakula also will have a relatively small surface footprint, as approximately 55% of the mine’s tailings will be pumped back into underground workings

kamoa-kakula project | ivanhoe mines ltd

All long-lead items for Kakula’s initial 3.8-Mtpa processing plant now have been delivered to site with the exception of the transformers, which are currently en route and expected around the third week of October

On October 1, 2020, Ivanhoe Mines announced that underground development at the Kamoa-Kakula Copper Project totalled 2,069 metres in September, setting a new monthly record for the project and bringing the total underground development to more than 22.6 kilometres – approximately 7.0 kilometres, or 44% ahead of schedule

The project’s monthly total of 2,069 metres of underground development is comprised of 1,696 metres at the Kakula Mine and 373 metres at the Kansoko Mine, which is located at the Kamoa Deposit – approximately 10 kilometres north of the Kakula Mine

Several underground development headings at the Kakula Mine now have transitioned into the higher-grade ore zones near the centre of the deposit, grading between approximately +5% copper and +8% copper. October will be the first month of mining in Kakula’s high-grade ore from the southern access drives, and this ore will be stored on a separate high-grade surface stockpile near the southern decline. Mining on the northern side of the orebody also will soon intersect the higher grade ore

kamoa-kakula project | ivanhoe mines ltd

The main access drives between northern and southern declines have less than 520 metres remaining before they connect in the high-grade centre of the deposit. The connection is expected to occur next month and will significantly increase ventilation to the centre of the orebody, allowing for additional mining crews to begin work in Kakula’s high-grade ore zones

In addition to driving the main connecting access drives, underground mining crews at Kakula are focused on preparation work for developing the high grade, drift-and-fill stoping blocks in the centre of the orebody, where the average grade is up to +8% copper. Opening up of the mining footprint for these high-grade stoping areas entails development work in areas of low-, medium- and high-grade ore, and is designed to coincide with the start-up of the processing plant next year. This will allow mining crews to deliver high-grade stoping ore directly from the underground to the processing plant

Drift-and-fill stoping is a highly-efficient form of underground mechanized mining and will allow the operation to efficiently recover significantly more tonnes from the orebody. Once drift-and-fill stoping operations begin, mining at the Kakula Mine will produce a significantly higher proportion of high-grade stoping ore than lower-grade development ore

kamoa-kakula project | ivanhoe mines ltd

Underground development at the Kansoko Mine currently is in low-to-medium-grade ore zones, grading between approximately +2% and +3% copper. Kansoko is being developed by training crews and will be a supplemental source of ore when the Kakula concentrator processing capacity doubles to 7.6 Mtpa − currently planned to be commissioned in Q2 2022

In September, mining crews at the Kakula and Kansoko mines produced and transported to surface approximately 132,000 tonnes of ore, bringing the project’s total pre-production ore stockpiles to an estimated 803,000 tonnes. September’s ore production is approximately 24% higher than August

The ore being mined from the northern portion of the Kakula Mine is transported to surface via the conveyor system and placed on a blended surface stockpile that now contains 540,000 tonnes grading an estimated 3.73% copper; comprised of 125,000 tonnes of high-grade ore grading 6.00% copper, and 415,000 tonnes of medium-grade ore grading 3.05% copper

kamoa-kakula project | ivanhoe mines ltd

Two additional, pre-production ore stockpiles are located at the Kakula South decline (approximately 168,000 tonnes grading 2.73% copper) and the Kansoko decline (approximately 95,000 tonnes grading 2.34% copper)

In September 2020, Ivanhoe Mines announced extremely positive findings of an independent definitive feasibility study (DFS) for the development of the Kakula Copper Mine; together with an updated pre-feasibility study (PFS) that includes ore mined from the nearby Kansoko Copper Mine in addition to ore mined from Kakula; and an updated, expanded preliminary economic assessment (PEA) for the overall development plan of all the copper discoveries made to date at the Kamoa-Kakula Project on the Central African Copperbelt in the DRC

The DFS, PFS and updated PEA, collectively referred to as the Kamoa-Kakula Integrated Development Plan 2020 (Kamoa-Kakula IDP20), build on the excellent results of the previous studies announced in February 2019. The new DFS incorporates the advancement of development and construction activities to date, and has once again confirmed the outstanding economics of the first phase Kakula Mine. As well, the expanded PEA shows the excellent potential to develop the project to a much larger scale and with a significantly larger production capacity

kamoa-kakula project | ivanhoe mines ltd

The Kamoa-Kakula IDP20, which includes the Kakula 2020 DFS, Kakula-Kansoko 2020 PFS and Kamoa-Kakula 2020 PEA, was independently prepared on a 100%-basis by OreWin Pty Ltd. of Adelaide, Australia; China Nerin Engineering Co., Ltd., of Jiangxi, China; DRA Global of Johannesburg, South Africa; Epoch Resources of Johannesburg, South Africa; Golder Associates Africa of Midrand, South Africa; KGHM Cuprum R&D Centre Ltd. of Wroclaw, Poland; Outotec Oyj of Helsinki, Finland; Paterson and Cooke of Cape Town, South Africa; Stantec Consulting International LLC of Phoenix, USA; SRK Consulting Inc. of Johannesburg, South Africa; and Wood plc of Reno, USA

The Kamoa-Kakula 2020 PEA is preliminary in nature and includes an economic analysis that is based, in part, on Inferred Mineral Resources. Inferred Mineral Resources are considered too speculative geologically for the application of economic considerations that would allow them to be categorized as Mineral Reserves – and there is no certainty that the results will be realized. Mineral Resources do not have demonstrated economic viability and are not Mineral Reserves

Figure 2. Overview of deposits included within the Kakula 2020 DFS(6 Mtpa ─ outlined by blue dotted line), Kakula-Kansoko 2020 PFS (7.6 Mtpa ─ outlined by purple dotted line) and Kamoa-Kakula 2020 PEA (outlined by green dotted line).Figure by OreWin 2020

kamoa-kakula project | ivanhoe mines ltd

The study evaluates the development of a stage one, 6-Mtpa underground mine and surface processing complex at the Kakula Deposit of 7.6 Mtpa, built in two modules of 3.8 Mtpa, with the first already under advanced construction. The first module of 3.8 Mtpa commences production in Q3 2021, and the second in Q1 2023. The life-of-mine production scenario provides for 110 million tonnes to be mined at an average grade of 5.22% copper, producing 8.5 million tonnes of high-grade copper concentrate, containing approximately 10.8 billion pounds of copper

The economic analysis uses a consensus, real long-term copper price of US$3.10/lb. (excluding inflation) and returns an after-tax NPV at an 8% discount rate of US$5.5 billion. It has an after-tax IRR of 77.0% and a payback period of 2.3 years

The estimated remaining initial capital cost, including contingency, is US$0.65 billion from July 1, 2020. The capital expenditure for off-site power, which is included in the remaining initial capital cost, includes advances to the DRC state-owned electricity company, Société Nationale d'Electricité (SNEL), to upgrade two hydropower plants (Koni and Mwadingusha) to provide the Kamoa-Kakula Project with access to clean electricity for its planned operations. The hydro-power upgrading work is being led by Stucky Ltd., of Renens, Switzerland, and the advance payments will be recovered by Kamoa-Kakula through a reduction in the power tariffs paid

kamoa-kakula project | ivanhoe mines ltd

Aerial picture of the Mwadingusha hydro-electric dam and power plant, with the new installed penstocks. Mwadingusha will soon be delivering 72 megawatts (MW) of clean, sustainable hydro-electricity to the national grid. The Kakula Mine is scheduled to be energized with permanent, 220-kilovolt (kV), hydro-generated power from the national grid in early 2021

The Kamoa-Kakula 2020 PEA also assesses an additional development option of mining several deposits on the Kamoa-Kakula Project as an integrated, 19-Mtpa mining, processing and smelting complex, built in multiple stages. This scenario envisages the construction and operation of three separate mines: first, an initial 6-Mtpa mining operation would be established at the Kakula Mine on the Kakula Deposit; this is followed by a subsequent, separate 6-Mtpa mining operation at the Kansoko Mine, where two crews are working already; a third 6-Mtpa mine then will be established at the Kakula West Mine, in addition to a fourth initial mine in the Kamoa North area operating initially at 1 Mtpa. The processing plant is constructed in five modules of 3.8 Mtpa, with an ultimate capacity of 19 Mtpa

As the resources at the Kakula, Kansoko and Kakula West mines are mined out, production would begin sequentially at five other mines in the Kamoa North area to maintain throughput of 19 Mtpa to the then existing concentrator and smelter complex, as illustrated in Figure 1

kamoa-kakula project | ivanhoe mines ltd

Each mining operation is expected to be a separate underground mine with a shared processing facility and surface infrastructure located at Kakula. Material will be transported to the Kakula processing complex by a system of overland conveyors. Included in this scenario is the construction of a direct-to-blister copper smelter with a capacity of one million tonnes of copper concentrate per annum

The Kamoa-Kakula 2020 PEA is preliminary in nature and includes an economic analysis that is based, in part, on Inferred Mineral Resources. Inferred Mineral Resources are considered too speculative geologically for the application of economic considerations that would allow them to be categorized as Mineral Reserves – and there is no certainty that the results will be realized. Mineral Resources do not have demonstrated economic viability and are not Mineral Reserves

Ultra-high-grade drill core, comprised almost entirely of chalcocite, from a hole drilled at Kamoa North. Kamoa North is an important source of high-grade ore in Kamoa-Kakula’s expanded 19 Mtpa development scenario. Chalcocite has the greatest percentage of copper of all the common sulphide-copper-bearing minerals ─ almost 80% copper by weight

kamoa-kakula project | ivanhoe mines ltd

In February 2020, Ivanhoe announced an updated Indicated and Inferred Mineral Resource estimate for the Kamoa Deposit that includes resources in the new Kamoa North Bonanza Zone and the Kamoa Far North Zone. The new Kamoa Mineral Resource estimate has an effective date of January 30, 2020 and was prepared by George Gilchrist, Ivanhoe Mines’ Vice President, Mineral Resources, under the direction of Gordon Seibel, RM SME, of the Wood Group (formerly Amec Foster Wheeler), of Reno, USA , and is reported in accordance with the 2014 CIM Definition Standards for Mineral Resources and Mineral Reserves. Mr. Seibel is the Qualified Person for the estimate

The project's geological team also updated the Mineral Resource estimate for the Kakula Deposit. This updated estimate has an effective date of November 2018. Effective January 30, 2020, the total, combined Indicated and Inferred Mineral Resources for the Kamoa-Kakula Project is shown in Table 8. Tables showing the Indicated and Inferred Mineral Resources separately for the Kamoa and Kakula deposits, as well as the sensitivity of Mineral Resources to cut-off grade, are shown in the appendices to this release

latest news

Copyright © 2021.Henan Expert Mining Machinery Co., ltd. All rights reserved. Sitemap

gotop